How to Maintain a Twin screw floating fish feed pellet extruder machine?

2026/10/27

ข่าวบริษัทล่าสุดเกี่ยวกับ How to Maintain a Twin screw floating fish feed pellet extruder machine?
Quick answer

Check screws, cutter gap and valves at every restart. Record current, oil pump pressure and bearing temperature every shift. Grease the conditioner gear weekly, measure wear monthly, change gearbox oil at 500 hours, empty the barrel before a long shutdown, and replace wear parts from the discharge end.

Twin screw floating fish feed pellet making machine maintenance follows a fixed set of intervals that a shift team can hold. A machine at 20 hours a day reaches the 500-hour oil change in about 25 days, and a cutter gap that has drifted shows in pellet quality and in motor current before it shows as a breakdown.

The work is ordered by interval, from every restart to the yearly overhaul, and each interval names the parts to touch and the readings to write down.

Key takeaways
  • Gearbox bearing grease is fully changed at 500 running hours, and a new machine gets its first change at 200 hours.
  • The differential conditioner front gear is greased weekly, the feeder gear motor every three months, and each motor once a year at overhaul.
  • Belt tension is set at 27 kg at the midpoint of the straight run, with 21 mm of deflection, or 16 mm per metre of span.
  • Wear parts are replaced from the discharge end, one type at a time, so each change can be traced.
  • A barrel left full during a long shutdown or a feed change carries the previous feed into the next batch.

Check the Screws, Cutter Gap and Valves Each Time You Restart a Twin-Screw floating Fish Feed Extruder

Three checks belong to every restart, and all three are made with the main power off.

Open the barrel and look for foreign material in the two screws, in the intermeshing zone and in the feeder hopper. Each cutter blade must sit at the same gap from the die core plane. Do not close a gap by loading a blade against the die face, because that load passes into the blade shaft and the die surface.

Confirm every valve is in the position used in the last run, then check the steam, water and lubrication lines for leaks at the joints. After the checks, close the barrel, switch on the main power, start the temperature control and read every instrument before the first material enters. Checks for the rest of the line are covered in the guide to daily maintenance and troubleshooting for a fish feed pellet production line.

Table 1 gives the wet-type twin-screw range.

Table 1. Wet-type twin-screw fish feed extruder range

Model
Output
Main motor
Cutter
Feeder
Conditioner
Type 65
250–300 kg/h
22 kW
1.5 kW
1.5 kW
3 kW
Type 70
500–600 kg/h
45 kW
1.5 kW
1.5 kW
3 kW
Type 85
1200–1500 kg/h
90 kW
3 kW
2.2 kW
5.5 kW
Type 95
2000–2500 kg/h
110 kW
3 kW
3 kW
11 kW
Type 120
3000–4000 kg/h
160 kW
5.5 kW
3 kW
15 + 7.5 kW

To have these intervals matched to one machine, send the output range, the main motor rating and the hours since the last gearbox oil change through the contact page.

ข่าว บริษัท ล่าสุดเกี่ยวกับ How to Maintain a Twin screw floating fish feed pellet extruder machine?  0

ข่าว บริษัท ล่าสุดเกี่ยวกับ How to Maintain a Twin screw floating fish feed pellet extruder machine?  1

Record Current, Oil Pump Pressure and Bearing Temperature on Every Shift

Four readings at fixed points in the shift give the first indication that load has changed.

  • Main motor current, at a steady feed rate, near the start and near the end of the shift.
  • Oil pump pressure, with the pump running and before the main motor is loaded.
  • Bearing and gearbox temperature, at the motor bearings, the gearbox case and the discharge end.
  • Discharge condition: pellet shape, pellet surface and the quality of the cut.

A current reading that rises at the same feed rate, recipe and screw speed points to a change in the Twin screw floating fish feed production machine or in the material. Write the four readings in the same row as the recipe code and the feed rate. Barrel temperature is the fifth record, and how the processing temperature of an extruded feed is controlled covers how each section is held during a run.

Sound is the sixth input: a note that changes while the feed rate does not calls for a stop and an inspection. Watch current, raw material, finished product, the oil circuit and the barrel temperature together, because one reading on its own does not identify a cause.

Apply Grease Weekly to the Conditioner Gear and Check Belt Tension

Two jobs sit on the weekly list: one grease point and one belt check.

Apply grease to the front-section gear of the differential conditioner once a week. The interval is fixed at one week and does not change with output.

Belt tension is checked with a spring scale. Apply 27 kg at the midpoint of the straight run between the two pulleys and read the deflection: 21 mm for a V-belt, and 16 mm per metre on a measured span. A belt that deflects more than the target slips at the pulley, which reduces the drive to the conditioner. Less deflection than the target puts a continuous load on the pulley bearings.

Measure Screw and Barrel Wear Once a Month on a twin-screw fish feed extruder machine

Monthly Twin screw fish feed making machine maintenance is measurement work.

With the main power locked off and the barrel open, measure the wear on the screws and the screw sleeves, and the clearance between the screw outside diameter and the barrel inner wall. Use the same points each month and write the numbers in the same record. One reading has no meaning on its own; the trend across three or four months shows whether a clearance is opening.

On an intermeshing twin screw, the clearance between the two screws and the clearance between screw and barrel both control how much pressure the barrel can build at the die. When a recipe that reached a given expansion no longer reaches it at the same temperature, moisture and screw speed, worn screws are one of the causes to check.

Do not use a hammer or a hard object on a screw or a sleeve, and do not place weights on or stand on the barrel. Screen the raw material and pass it over a magnet, so metal does not reach the feeder. Wear locations on a twin-screw machine differ from those on a single-screw machine, as set out in the comparison of single-screw and twin-screw fish feed extruders.

Change the Gearbox Bearing Grease at 500 Hours and Grease the Motors Once a Year

Box bearings get a full grease change at 500 running hours. A new Twin screw fish feed pellet maker machine gets its first change at 200 hours. The conditioner front gear takes grease weekly, the feeder gear motor every three months, and each motor once a year.

Running hours, not calendar time, set the gearbox interval. A machine at 20 hours a day reaches 500 hours in about 25 days. The 500-hour change covers all the lubricating grease in the gearbox bearings. On a new machine, add grease before the first run and change the oil at 200 hours.

Check oil condition and level often, and top up with machine oil whenever the level falls. If the oil has emulsified or changed colour, find the cause before more oil goes in. Motor grease is an annual item added during the overhaul.

Table 2. Lubrication points and intervals

Point
Interval
Action
Check
Gearbox bearings
500 running hours; 200 hours on a new machine
Full change of the bearing grease
Oil level against the sight mark; oil condition before draining
Differential conditioner front gear
Weekly
Apply grease to the gear
Grease present across the gear face
Feeder gear motor
Every three months
Top up grease as condition requires
Grease condition at the plug
Each motor
Once a year, at the annual overhaul
Add high-speed grease
Bearing sound and bearing temperature after restart
Oil quality and oil level
At any time, checked every shift
Top up with machine oil
Colour, emulsification, level against the mark

Grease grade changes the interval. Send the grade in use, the hours on the gearbox since the last change and the colour of the oil on the dipstick through the contact page, and the next change point can be set from the machine documents.

Empty the Twin screw floating fish feed pellet mill Barrel Before a Long Shutdown or a Feed Change

Emptying the barrel before a long shutdown or a feed change prevents caking inside the barrel, mould growth and cross-contamination between feeds.

The shutdown sequence has nine steps:

  1. Stop the feeder.
  2. Run the main motor at low speed to discharge the material in the barrel.
  3. Stop the cutter.
  4. Remove the die without delay.
  5. Run the main motor at low speed until the barrel is empty.
  6. Stop the machine.
  7. Blow the dust out of the control cabinet.
  8. Switch off the main power.
  9. Clean the area around the machine.

An abnormal stop, such as a power failure, follows a shorter sequence. Remove the die immediately and discharge the material slowly. If the main motor will not turn, do not force a start.

For a feed change, clean the die, cutter and barrel once the barrel is empty, then inspect all three.

Replace Twin screw floating fish feed pellet maker machine Wear Parts From the Discharge End and One Type at a Time

Parts near the discharge end wear faster than parts at the feed end, so replacement starts at the die and works back toward the feeder.

The order:

  1. Record the running hours, the part type and the readings from the last shift.
  2. Remove the die and the cutter.
  3. Replace the worn part that sits closest to the discharge end.
  4. Run the machine and record current, temperature and pellet condition for one full shift.
  5. Move one position toward the feed end and repeat.

Changing more than one type of part at the same time removes the reference. If output or pellet quality changes after the work, the change cannot be assigned to a single part. Where several parts sit at their limit together, change them in stages and write the readings after each stage.

No hammer or hard object on a screw or a sleeve during the work. The die, cutter and pellet at the outlet can be compared with the test run of a wet-type twin-screw floating fish feed extruder. Wear part records also set the interval for the next part.

Conclusion

TheTwin screw floating fish food maker machine maintenance cycle here fits inside a shift rota: three checks at restart, four readings per shift, one grease point per week, one measurement per month, one oil change at 500 hours, and a full barrel empty at every shutdown.

The two items most often deferred are the conditioner gear grease and the monthly wear measurement. Both take less than an hour when scheduled, and both appear in pellet quality when missed.

Start with the interval you can hold this week, then add the next one.

Send the model class and the wear part records. A replacement plan is set from the output class, the hours at each past replacement and the parts changed at the last shutdown. Send those three items through the contact page, or review the 500–800 kg/h stainless steel twin-screw floating fish feed extruder for that output class.

Frequently asked questions

Twin-Screw Fish Feed Extruder Maintenance: Common Questions

How do I set a Twin screw floating fish  machine maintenance schedule?

Start from the intervals in the machine documents, then adjust with the readings. A machine at 20 hours a day reaches the 500-hour oil change in about 25 days, so the calendar interval follows the shift pattern.

The oil has turned dark before 500 hours. Should it be changed?

Colour alone does not set the change point. Check the level, look for emulsification and compare with the oil taken at the last change. If the oil is milky, or metal particles are visible, find the cause and change it before 500 hours.

When should wear parts be replaced?

Replace a part when the measured clearance no longer builds the pressure and expansion the recipe needs at the same temperature, moisture and screw speed. Replace it also when cut quality cannot be held with a correct cutter gap. The clearance limit is specific to the machine size and is stated in the machine documents for the installed size.

Can the whole screw set be replaced at once?

Replace one type of part at a time, starting from the discharge end. A full set changed in one operation removes the reference for the next interval, and the effect of each part cannot be separated.

Should the screws be removed for a long shutdown?

The shutdown steps do not include removing the screws. The sequence runs from the feeder stop to the power switch: discharge at low speed, stop the cutter, remove the die, run the barrel empty, stop the machine, clean the control cabinet. The die and cutter are cleaned before the next run.

Which numbers should be written down every shift?

Main motor current, oil pump pressure, motor and gearbox temperature, and the discharge condition. Add the feed rate and the recipe code to the same row. Without those two, a current reading cannot be compared with the previous shift.

Does the gearbox oil need changing when the raw material changes?

The gearbox is a closed system and its interval is set by running hours. A feed change calls for the barrel to be emptied and the die and cutter to be cleaned. Oil condition is checked at the same time, and an emulsified or discoloured oil is investigated before the next run.